Sunday, October 31, 2010

A few indoor shots

Upon checking the outside of the house this morning I discovered to my horror that the side door was unlocked. I was really concerned as we had the Homestead sign dumped on our front lawn overnight by some kids, thankfully every thing is OK. But now it's given me a chance to have some real quite time in the house and do some measuring up and happy snaps.







Thursday, October 28, 2010

Panel Door on

Another big item was finally added today, the panel lift door for the garage went on and I am very happy with the colour. The range hood was fitted yesterday and the kitchen is starting to come together slowly.





Sunday, October 24, 2010

The cleaning and detailing has begun

Gas main connected, plumbing all finished, shower screens fitted and I have installed the storm water down the muddy side of the house. Got a phone call from the SS on Friday telling that the cleaners will be in on the weekend and the practical completion inspection will happen on Monday. Booked in the flooring people for the 17th of Nov. and the air-conditioner (evaporative ducted) will be fitted last week of November.

Some pictures will be posted when the cleaning is finished.

Sunday, October 10, 2010

Power, tiles and painted

Last week the painter and tiler started, this week they have finished. The electrical is 99% done, and on Saturday the guy measured up for the shower screens. So now it's just the final fit out for the bathrooms, panel lift door fitment, kitchen range / range hood fitment, mains gas and a really good clean up. So at this stage we are looking at a hand over date of early Nov, approx 2 months early. Deposit paid on flooring, aircond and paving, fencing tba.