Sunday, November 21, 2010

Floors are done and dusty (very dusty)

Floors went  down this week, the floor shows up dust from the outside very easily but just as easy to remove. The flooring is vinyl plank flooring done by Carpet Choice Edwardstown, we are happy with the look but the room needs quite a bit of work to make it home  We went dark with the carpet as a feature because we only have carpet in a few room.




Tuesday, November 9, 2010

Yee Haaa, we've crosed the finish line

We got the keys to our new house yesterday, our journey has crossed a major mile stone, not the last one but one of great significance. Everything went well at handover, the SS even fixed a couple of small things whilst he was there. The only "major" issue was the lack of automatic roller door controls, a simple over sight that will be rectified in a few days. Other than that we are very happy and we now have an up hill climb to get all the outside bits finished and keep the dirt out.

Sunday, October 31, 2010

A few indoor shots

Upon checking the outside of the house this morning I discovered to my horror that the side door was unlocked. I was really concerned as we had the Homestead sign dumped on our front lawn overnight by some kids, thankfully every thing is OK. But now it's given me a chance to have some real quite time in the house and do some measuring up and happy snaps.







Thursday, October 28, 2010

Panel Door on

Another big item was finally added today, the panel lift door for the garage went on and I am very happy with the colour. The range hood was fitted yesterday and the kitchen is starting to come together slowly.





Sunday, October 24, 2010

The cleaning and detailing has begun

Gas main connected, plumbing all finished, shower screens fitted and I have installed the storm water down the muddy side of the house. Got a phone call from the SS on Friday telling that the cleaners will be in on the weekend and the practical completion inspection will happen on Monday. Booked in the flooring people for the 17th of Nov. and the air-conditioner (evaporative ducted) will be fitted last week of November.

Some pictures will be posted when the cleaning is finished.

Sunday, October 10, 2010

Power, tiles and painted

Last week the painter and tiler started, this week they have finished. The electrical is 99% done, and on Saturday the guy measured up for the shower screens. So now it's just the final fit out for the bathrooms, panel lift door fitment, kitchen range / range hood fitment, mains gas and a really good clean up. So at this stage we are looking at a hand over date of early Nov, approx 2 months early. Deposit paid on flooring, aircond and paving, fencing tba.

Thursday, September 30, 2010

Painting has begun

Things are happening so quick I can barely keep up, almost everyday there has been some level of work being started or completed. Yesterday morning I see them rendering the front pillars, thinking great they will paint them probably next week, get home tonight and there are painted.

Anyway here's the front of house again, getting closer to what it will look like finished. The panel door will be paper bark, same as fascia's.