Sunday, August 29, 2010

Bricks, electrical, plumbing and MUD

Bricks are on site and what mess we have in our front yard. Wettest August since 1992 and it's a quagmire. I'm feeling sorry for the brickies already. The electrical is finished, although we need one small amendment made in the home theatre. Plumbing is done and looking good. The roof tilers finished last week but have not taken down the safety railing yet. All looking good and winter can't go on much longer.

Wednesday, August 11, 2010

Roof tiles and mud

We had our tiles delivered Monday and they started putting up the tiles today. Looks like the truck delivering them had a time of it, at least my un-compacted trench is slightly more compacted now. The tiles look a lot lighter than I thought they would, maybe just the angle of the light and time day (late).